| Completing the CTBT's Verification Regime: Progress and Challenges
|
| |
| Trevor Findlay and Oliver Meier |
| |
| INTRODUCTION |
| Four years after the
Comprehensive Nuclear Test Ban Treaty (CTBT) was opened for signature, the
treaty's verification system is being progressively established. After a slow
start, which was mainly due to the novelty of setting up a verification system
based on a global network of monitoring stations, implementation is now making
good progress. The Preparatory Commission (PrepCom), which marked its third
anniversary in April 2000, and the Provisional Technical Secretariat (PTS),
both of which are in charge of setting up the International Monitoring System
(IMS) and its associated components, have identified the major hurdles which
stand in the way of completing the system and have begun to allocate resources
accordingly. The Provisional CTBTO is evolving quickly into a fully-fledged
international organisation. As of 25 September 2000 the PTS employed 242 staff
from 70 signatory states-making it more than two-thirds complete. Although
there are still political and technical hurdles to be overcome, such as the
development of on-site inspection arrangements, the PTS could complete its work
before the treaty enters into force. This will, however, require the
undiminished political, technical and financial support of all states
signatories. |
| |
| THE
INTERNATIONAL MONITORING SYSTEM (IMS) |
| Background |
| The IMS will consist of 321
monitoring stations and 16 radionuclide laboratories located in some 90
countries. Some of these already exist, while others will have to be
constructed. Two hundred and one of these stations belong to the primary
network, which will be providing data to the IDC which has been collected on a
continuous, round-the-clock basis. In many cases IMS stations use existing
infrastructure, upgraded and certified for use by the IMS. Sixty-two per cent
of the network of 120 auxiliary seismic stations, which will supply data only
on request, essentially meet technical specifications already. |
| Four types of stations are to be
established?seismological, infrasound, hydroacoustic and radionuclide. The
seismic network will form the core of the verification system. Seismic waves
generated by earthquakes, explosions or other phenomena will be detected using
50 primary and 120 auxiliary seismic stations, distributed worldwide. In
addition, 11 underwater hydroacoustic stations are being set up. Sixty
land-based infrasound stations will use sonar to detect atmospheric tests,
while 80 radionuclide stations will measure radioactive particles in the
atmosphere from atmospheric nuclear tests or underground tests that vent.
Sixteen radionuclide laboratories will analyse filters from the stations, as
well as samples taken by inspectors. |
| The four different technologies
operated by the IMS are complementary and are able to detect tests in different
environments. Seismic monitoring is best at detecting underground tests -
although it might also be able to discern atmospheric tests conducted at low
altitudes. Hydroacoustic technology primarily monitors the oceans and
infrasound is most efficient at detecting atmospheric tests - although it may
also detect some underwater and shallow underground events. Seismic and
acoustic detection technologies under specific circumstances might not provide
enough conclusive data to reveal whether a large conventional explosion or
small nuclear test has taken place. Radionuclide stations could be the most
powerful tool in clarifying the nature of an event by detecting radioactive
particles. |
| The four different technologies
operated by the IMS are complementary and are able to detect tests in different
environments. Seismic monitoring is best at detecting underground
tests?although it might also be able to discern atmospheric tests conducted at
low altitudes. Hydroacoustic technology primarily monitors the oceans and
infrasound is most efficient at detecting atmospheric tests?although it may
also detect some underwater and shallow underground events. Seismic and
acoustic detection technologies under specific circumstances might not provide
enough conclusive data to reveal whether a large conventional explosion or
small nuclear test has taken place. Radionuclide stations could be the most
powerful tool in clarifying the nature of an event by detecting radioactive
particles. |
| States parties may also
contribute data to the IMS from so-called Co-operating National Facilities
(CNFs). CNFs are national stations which can be called on by the CTBTO to
clarify suspicious events. Such stations are operated by treaty parties but
have undergone the same certification procedures, including the authentication
of communication links, as IMS station. |
| |
| Progress in station
establishment and certification |
| After a slow start, the setting
up of the required IMS stations is progressing steadily. In the early days of
the PTS, many legal and bureaucratic hurdles had to be overcome before
construction and/or certification of a station could begin. The PTS first had
to establish the legal procedures for setting up stations and establish links
with National Authorities and scientific co-operating partners in IMS
participating countries. |
| Another impediment is the complex
certification process. In order to certify a station, the PTS has to be assured
that technical specifications are substantially met and data from the stations
can be authenticated. Finally, a proper link to the global communications
infrastructure (GCI) has to be established. Setting up a new IMS station
from the planning stage to certification takes at least two
years. |
| On 28 July 2000, the first three
IMS stations (primary seismic facilities in Canada, Norway and the United
States) were certified. The PTS estimates that the number of IMS station that
have a site survey completed, are installed, or are certified, will increase
dramatically over the next couple of years. As the figures below show, this is
true for all four monitoring technologies. Current plans are that by the end of
2001, ninety-six per cent of site surveys will be completed, 56 per cent of
stations will be installed and sending data to the IDC, and 41 per cent of the
stations will have been certified.1 |
| Calibration of IMS stations has
been slow. Four conventional explosions have been conducted to calibrate IMS
stations, three in Kazakhstan, in cooperation with the United States, and one
in the Red Sea conducted by Israel. An explosion in Kazakhstan in October 1999
was also used for an on-site inspection exercise by the PTS. The most recent
explosion in Kazakhstan destroyed the last tunnel at the former Soviet nuclear
test site Semipalatinsk, which is now officially dismantled. |
| |
 |
| |
 |
|
| |
 |
 |
| Legal frameworks
|
| Certification of stations must be
covered by an agreed legal framework, 'facility agreements or arrangements',
between the PrepCom and host states. These must be approved by the PrepCom if
they differ substantially from the model agreement provided by the Secretariat.
The Executive Secretary of the PTS has urged those governments that have not
yet negotiated facility agreements to do so.2 So
far, fourteen have been concluded. Two hundred and eighty IMS facilities in 60
countries were covered by some kind of legal arrangement by the end of
September 2000.3 Site surveys for 125 of the 201
IMS stations in the primary network are complete.4
|
| For about 30 stations, and one
radionuclide laboratory, new sites had to be found when site surveys revealed
that the co-ordinates given in Annex 2 of the treaty were unsuitable. The
reasons included excessive background noise or because the locations were at
sea or in other unsuitable areas.5 |
| |
| International Data Centre
(IDC) and Global Communications Infrastructure (GCI) |
| Integrating data on a large scale
from many different sources poses a completely new monitoring and verification
challenge to an international organisation, but is also likely to result in
great synergies. The IDC, which is being progressively commissioned in Vienna,
will receive and process data from all IMS monitoring facilities via a
dedicated Global Communications Infrastructure (GCI). |
| The GCI will use very small
aperture terminals (VSATs) to ensure the swift and secure transport of up to
11.4 gigabytes of data between facilities, the IDC and states parties. By March
2000, VSATs had been installed at 25 IMS facilities. Fifty are expected to be
installed by the end of 2000.6 Three communications
'hubs', which receive data from IMS stations in a particular region and forward
it to the IDC, are located in Germany (European hub), Italy (Atlantic and
Indian Ocean hubs) and California (Pacific Ocean hub). They are all complete
and transmitting data. |
| Data from seismic and acoustic
stations will be received by the IDC in near real time and be available within
a few hours to states parties which wish to receive it. Data processing will be
largely automated. The second of four software releases for this purpose was
installed at the IDC in late 1999. On 20 February 2000 the IDC assumed
responsibility for collecting and disseminating data from the IMS stations in
operation. Of the 201 stations in the primary network, 32 are sending data to
the IDC. This number is expected to rise sharply over the next few years, with
more than 50 per cent of stations reporting to the IDC by the end of
2001. |
| Unlike the four types of 'wave
form' data, radionuclide data will be available after a delay of several days
because samples have to be physically collected and analysed. New technologies
currently being developed may automate data transmission from stations in
remote areas, but this will not shorten the time necessary for analysis.
|
| It is the IDC's responsibility to
screen out events which are clearly of natural origin, as well as those which
are clearly non-nuclear and man-made, such as large conventional explosions. A
large percentage of all earthquakes, for instance, occur at depths at which it
is impossible to conduct clandestine nuclear tests. By applying screening
criteria to the vast amount of data delivered to the IMS, the number of
potentially suspicious events can be dramatically reduced. The IDC will issue
Standard Event Bulletins, which indicate the degree to which each detected
event meets specific screening criteria.7 States
without significant national technical and analytical means will naturally look
to the IDC for more precise information if suspicions are aroused concerning a
particular event. The IDC is expected to assist any state party in the
technical analysis of IMS data as well as data provided by other states
parties.8 |
| Forty-four signatory states are
currently receiving IMS data and 'products' on a trial basis. On 21 February
2000 the IDC started to distribute Reviewed Event Bulletins (REBs) to member
states. They have been issued daily for the past few months, even though this
was not planned for the current Phase 4 of the establishment of the IDC. Due to
a shortage of staff and the constraints of a 5-day working week, REBs are
currently being distributed with several days' delay. |
| Some member states have urged the
PTS to ensure that the IDC distributes products on a more timely basis. In
order to do this under current operational limitations, PrepCom Working Group B
(responsible for verification) suggested the IDC do this for 5 daily REBs per
week. This will be done by expanding the IDC's work schedule to a 6-day working
week. The immediate goal is to demonstrate that the IDC is capable of
distributing data in near-real time, around the clock, without implementing
this on a permanent basis prior to entry into force. It is planned that during
Phase 5 of the IDC's installation (commencing in early 2001), the timely
production of REBs will be increased from 5 to 7 per week. |
| To evaluate the work of the IDC,
Working Group B has commissioned an external expert evaluation. Led by the UK's
Ian Kenyon, formerly of the Organization for the Prohibition of Chemical
Weapons (OPCW), six international experts will spend two to three weeks in
Vienna to evaluate whether the IDC is fulfilling its mandate and what possible
improvements could be made. Topics to be considered by the Evaluation Team
include: the implementation of PrepCom guidelines by the IDC; the overall state
of the IDC and the GCI; as well as the interaction between the IDC and other
parts of the PTS, states signatories and the broader scientific community; and
possible improvements in the scientific methods and software used by the IDC.
The experts will report to the PrepCom in November 2000. If successful,
external consultants might be used to evaluate other parts of the
PTS. |
| |
| THE
CONTRIBUTION OF NON-IMS CAPABILITIES |
| Member states can also submit
data from national technical means (NTM) of verification to the Executive
Council in the course of consultation and clarification procedures or to
support a request for an on-site inspection. It is likely that states will use
a very broad definition of NTM, enabling them to table almost any information
that they deem relevant and politically acceptable. Thus, a state could, for
example, table information from its own signals intelligence, satellite imagery
obtained from its own satellites or those operated commercially, or data
collected by scientists anywhere in the world. |
| Data from scientific networks
might carry greater weight because they will have been collected transparently
and been peer reviewed. In any case, whatever information states might table in
the Executive Council, suspicious events are likely to be detected, discussed,
analysed and evaluated outside the Council. As has happened in past, for
example when India and Pakistan conducted their nuclear tests in May 1998 and
when the US government accused Russia of having conducted clandestine nuclear
tests in August 1997, data from non-IMS stations will be distributed and
discussed widely within the international scientific community. |
| While the CTBT does not
explicitly ban nuclear test preparations, commercial satellite pictures can
provide an important addition to the IMS because they can detect such
preparations. Non-governmental organisations are already monitoring nuclear
test sites using such data.9 |
| The question is therefore not
whether non-IMS capabilities can strengthen monitoring of compliance with the
nuclear test ban but how this can be best achieved. Attempts to introduce new
monitoring techniques would complicate the task of the PrepCom as it seeks to
fully establish the verification system already provided for in the treaty. On
the other hand, the treaty does commit states parties to 'cooperate with the
Organization and with other States Parties in the improvement of the
verification regime and in the examination of the verification potential of
additional monitoring technologies
with a view to developing, when
appropriate, specific measures to enhance the efficient and effective
verification of this Treaty'.10 It specifically
mentions electromagnetic pulse detection and satellite monitoring in this
context. |
| |
| ISSUES TO BE
RESOLVED |
| On-Site Inspections
Manual |
| In parallel to setting up the
IMS, the PrepCom is also laying the groundwork for on-site inspections (OSIs).
OSIs may be ordered by the Executive Council to clarify suspicious events?on
the basis of signals detected by the IMS and /or information from NTMs
submitted by a state party. The CTBTO will not, unlike the OPCW, have a
standing OSI inspectorate, but will draw on a pool of trained inspectors
nominated by member states. This pool needs to be geographically representative
and large enough to provide a team of up to 40 inspectors within six days.
Inspectors will require a diverse range of skills and the ability to work in
harsh climates or terrain. By October 2000 one hundred and fifty participants
from 69 states signatories had successfully undertaken three introductory
courses conducted by the PTS. |
| OSI teams will be permitted to
spend up to 130 days on an inspected state's territory and will therefore
require significant in-country support. Substantial amounts of portable
equipment will also be needed, including geophysical and radionuclide
equipment, drilling equipment, communications equipment and the means to
conduct overflights. |
| The development of an Operations
Manual (OpsMan) for on-site inspections is proving one of the most difficult
areas of the PrepCom's work, largely because too many fundamental issues were
left unresolved by the treaty negotiators. While OSI provisions received
insufficient attention during the early days, when establishing the IMS was the
first priority, in November 1999 the PrepCom took steps to speed up the
development of OSI procedures. The budget for developing an OSI capacity was
doubled and a group of Friends of the OSI Programme Coordinator was
established, open to participation by all signatories, to draft a text for an
OSI manual. |
| This process faces several
difficulties. First, there is no agreed understanding of the scope and the
purpose of the manual. Israel, which is wary of intrusive OSIs for reasons
unrelated to the CTBT, favours a minutely detailed manual which explains the
purpose, methodology and parameters of the activities to be undertaken by
inspectors. Others, including the United States, prefer a manual that outlines
general responsibilities of the inspectors, but leaves room for flexibility and
is within the spirit of the treaty's OSI provisions. Specific questions which
need to be resolved include: should an inspection team only be allowed to look
for evidence relating to an ambiguous event, or should it be allowed to 'look
around' the inspection area? What kind of data should it be allowed to collect?
What kind of managed access provisions are necessary in case the team needs to
access or inspect a facility? What are the rules for inspecting so-called
restricted access areas?11 |
| Decisions about equipment to be
used by inspectors are also affected by disagreement about the nature of OSIs.
Thus, it has been argued that inspection equipment must not reveal information
irrelevant to the inspection's purpose. This has made it more difficult to use
off-the-shelf technology for OSIs, for example to analyse samples for
radionuclide traces. |
| Second, the development of the
manual has until very recently depended on national contributions, since the
PTS was not allowed to propose language. Fortunately, this is no longer the
case and the PTS has contributed several working papers to the OpsMan draft.
|
| Third, the current drafting
method, in which national contributions are simply compiled into a rolling text
that now amounts to 1,000 pages, is too slow and ineffective. Working Group B
has initiated a new process intended to speed up the drafting. Based on
contributions received so far, the Chairman of the Friends of the OSI Programme
Coordinator will compile a draft Rolling Text for the OpsMan with the
assistance of others. Discussions on the basis of this Rolling Text will be
initiated at a special meeting of Working Group B in February 2001. More time
in the intersessional periods has been allocated to the drafting process and it
is hoped that more delegations will be drawn into the drafting process at the
February meeting. |
| Finally, there is a danger of
linkage between completion of the OSI manual and entry into force of the
treaty. At least one state whose ratification is required for entry into force
has indicated that it might not ratify before substantial parts of the OSI
arrangements have been agreed. It would be deplorable if disagreement over the
least important element of the CTBT's verification system for day-to-day
monitoring of compliance were to delay entry into force. |
| Clearly, any attempt to
renegotiate the CTBT through the back door of negotiations on the OSI
provisions is a cause for concern. A flexible mandate for inspectors, within
clearly defined boundaries, will increase the chances that clandestine tests
are identified. Experience in other verification regimes also shows that many
of the fears articulated during treaty negotiations and the preparatory process
prior to entry into force turn out to be exaggerated when regimes begin
functioning. This is even true where intrusive inspections are conducted on a
regular basis and affect private companies, as is the case with the 1993
Chemical Weapons Convention. |
| |
| Confidentiality
Rules |
| Because the IDC will soon start
to distribute data and products to member states on a large scale
including daily 'Fused Event Bulletins', ad hoc event bulletins and
analyses of data the implementation of the 'confidentiality' provisions
of the treaty has become a controversial issue in the PrepCom. The treaty
itself provides only that it is the duty of the Technical Secretariat to 'make
available all data, both raw and processed, and any reporting products, to all
States Parties' (Article IV paragraph 14.e). It is unclear whether this
excludes the possibility of making information available to others. |
| Scientific and humanitarian
relief organisations are especially interested in receiving data from IMS
stations. Data from the seismic network is of interest to seismologists in
improving their ability to predict earthquakes and other natural phenomena.
Hydroacoustic stations could give early warning of tsunamis, while infrasound
stations could warn of volcanic eruptions. |
| China and other states have
argued that for security reasons access should be restricted to governments.
Some Western states and others favour a more open policy, arguing that IMS data
has little national security relevance. It will in any case be difficult to
prevent leakage of the data, since data centres in all CTBT parties will have
direct access to it. In order to evaluate confidentiality rules, the PTS is
planning a phased release of certain types of data to a limited number of
non-state recipients. Thus, humanitarian organisations could promptly receive
IMS data for disaster relief operations, while others would have only delayed
access. The proposed test of a delayed release of certain types of IMS data
beyond states parties' National Data Centres has not begun because of the
continued resistance of at least one state party. |
| |
| Costs |
| The 2000 PrepCom budget is $US
79.9 million, compared with $US 74.7 million in 1999 and $US 58.4 million in
1998. The collection rate for assessed contributions to the budget was
approximately 96 per cent for the 1999 budget and 92 per cent for 2000. This is
a good record compared with most international organisations, but needs to be
maintained. |
| Even though the PrepCom's two
Working Groups and the PrepCom itself still define the parameters of the work
of the PTS, it is gradually becoming more independent. While the PTS has
generally accepted responsibility for paying for the operating and maintenance
costs of primary IMS stations after certification, a question remains as to
whether it should wholly or partially pay the operating costs for auxiliary
seismic stations after their certification. These stations are 'dual use' and
mostly serve scientific purposes. They need to be certified by PTS, but will
only report to the IDC on request (for example to clarify a suspicious event).
|
| Some auxiliary stations are also
nominated to back up primary stations in case they cannot report. If entry into
force is substantially delayed, states might decide to switch off stations
already reporting to the IDC to save costs. One way to resolve this question
would be for the PTS to provide financial assistance to states having trouble
funding their auxiliary stations. |
| Cost estimates for non-seismic
stations made during negotiations on the CTBT have been consistently too low
because expenditures for installation, especially in remote locations, were not
taken into account and because little experience with novel monitoring
technologies existed. |
PrepCom 2000 Budget
($US 79.9 million) |
· $US 40.2 million for
establishing or upgrading IMS stations · $US 12.6 million for the
IDC · $US 7.3 million for establishing the global communications
infrastructure · $US 2.8 million towards developing an on-site
inspection capacity · $US 13 million on administration. |
| Source: CTBTO PrepCom document
CTBT/PC-10/1/Annex V '2000 Programme and Budget', Tenth Session, Vienna, 15-19
Nov. 1999. |
|
| In its 2001 budget projection the
PTS has called for a moderate increase to $US 94.9 million. Some signatories
have insisted on a smaller budget and it now seems more likely that the 2001
budget (which will be approved during the November 2000 session of the PrepCom)
will be in the order of $US 85 million. While it is positive that there will be
an increase in real terms compared to the 2000 budget, the fact that some
member states have again insisted on cuts is worrying, for several reasons.
|
| First, a static or shrinking PTS
budget is hard to reconcile with the investment required to have the
verification system fully functioning at entry into force. The PTS has
estimated that the investments necessary for fully establishing the IMS require
over $US 100 million per year for at least two years. |
| Second, budgetary pressures are
likely to increase as more IMS stations are certified and the PTS assumes
operational and maintenance costs for them. This will make it harder to
maintain a rising level of investment in new stations, an important yardstick
for assessing progress in completing the verification system. |
| Third, member states' insistence
on budget cuts may signal reduced political support for the treaty and its
verification system. It is especially worrisome if those states that are
otherwise prominent in promoting the nuclear disarmament agenda insist on
budget cuts. In some cases, attempts to micromanage the PTS budget have also
led to problems by limiting the time available for discussions on the future of
the PTS. In general the PTS should be given more leeway in managing its
budget. |
| |
| THE WAY
AHEAD |
| According to Article IV of the
CTBT, the IMS must be able to meet verification requirements at entry into
force of the treaty, which will occur six months after all 44 states required
to ratify the treaty have done so. From a legal perspective this requires that
all three operational manuals-for the IMS, the IDC and OSIs-are ready for
adoption by the first conference of states parties. In practical terms, it
means that the verification system needs to be workable and have global
coverage. |
| While the exact date of entry
into force is unpredictable, the PTS is now planning on the basis that the IMS
will need to be completed by 2005 at the latest. However, contingency plans
exist should entry into force be achieved earlier. This will depend on the
political support of signatories, as well as on their willingness to make the
necessary technical and financial contributions. |
| |
| References and
Footnotes |
| 1
Peter Basham, 'The Current Status of the CTBTO Monitoring System', Contribution
to the Independent Commission on CTBT Verifiability,
http://www.ctbtcommission.org/bashampaper.htm |
| 2
CTBTO PrepCom document CTBT/PC-9/1/Annex III, 2 Sept. 1999, p. 8. |
| 3
'Comprehensive Nuclear-Test-Ban Treaty - Four Years Old' Preparatory Commission
of the Comprehensive Nuclear-Test-Ban Treaty Organization, Provisional
Technical Secretariat, Press Release, 25 September 2000. |
| 4
Peter Basham, 'The Current Status of the CTBTO Monitoring System', Contribution
to the Independent Commission on CTBT Verifiability,
http://www.ctbtcommission.org/bashampaper.htm |
| 5
CTBTO PrepCom document CTBT/PC-10/1/Annex II, 24 Nov. 1999. |
| 6
Peter Basham, 'The Current Status of the CTBTO Monitoring System', Contribution
to the Independent Commission on CTBT Verifiability,
http://www.ctbtcommission.org/bashampaper.htm. |
| 7
Protocol to the CTBT, Part I, Section F, paragraph 18. |
| 8
Protocol to the CTBT, Part I, Section F, paragraph 20. |
| 9 The
Institute for Science and International Security, for example, has published
recent images of the Pakistani test site in the Kharan Desert on the internet.
These can be found at
http://www.isis-online.org/publications/southasia/satindex.html |
| 10
CTBT, Article IV.11. |
| 11 On
these questions see Mordechai Melamud, 'Background Paper on On-Site Inspections
(OSI) Main Elements and Expectations',
http://www.ctbtcommission.org/melamudpaper.htm |
| |